Case study on “data analytics is a team sport”: pair up analytical capabilities with domain and context expertise

Data on a crucial piece of global supply chain infrastructure

The Panama Canal plays a crucial role in the global supply chain infrastructure. It facilitates efficient goods transportation between Atlantic and Pacific.

Among supply chain professionals, the impact of the current El Niño-induced situation is well-known (see, for example, Maritime Executive on Oct 31 2023, The Economist on Nov 25th 2023, Fortune on Dec 4th 2023, Fortune on Jan 2nd 2024). Yet:

To our best understanding, we are the first to publish a quantitative analysis that shows the full extent of the upcoming challenges.

We will share concerning developments uncovered through our analysis of the historical water level data from the Gatún Lake. This artificial lake is a key component of canal operations. It provides the water necessary to operate the locks for the passage of ships through the canal. Throughout the year 2023, the canal has experienced unusually low water levels – impacting daily capacity, queuing times, and ship loading.

The studied data have a simple structure: a column with dates and another with water levels. Yet, even data as simple as these can’t be fully understood by simply feeding them into an AI or using plug-and-play machine learning algorithms. Instead, they must be analysed with curiosity, creativity, and in multiple loops of experimentation.

Damage done to a rainforest in weeks and months may necessitate centuries or a millennium to heal

Low water levels aren’t a problem solely associated with the Panama Canal. We have all seen recent pictures from the Amazon. Also other rivers, including the Rhine, have shown historically low levels.

The Gatún Lake is fed by rainwater. With almost 3000mm of rain per year Panama has the 5th highest level of annual precipitation on Earth (Worldbank indicator AG.LND.PRCP.MM).  The rainy season typically runs from May through December.

Past deforestation in the vicinity of Lake Gatún has decreased the water retention capacity of the lake’s surroundings. This has lead to detrimental consequences: During the rainy season, rapid rainfall runoffs into the lake have exacerbated erosion, aggravated the gradual sedimentation, and thus reduced the lake’s overall capacity.

Primary tropical rainforest can store for months vast amounts of water. Yet, the diminished rainforest cover around the lake, due to deforestation, has resulted, during the dry season, in reduced water replenishment from the forest into the lake.

To the best of our information (obtained during a tourist visit to the Panama Canal, thank you Michael Kierdorf ), the authorities are aware and have taken action. A secondary rainforest is planted and protected. However, tropical rainforest can be cleared in weeks or months, the soil then degrades in a matter of years, but it takes centuries or even more than 1000 years for such a forest to regain its full functionality (private communication Bodo Frommelt).

An unprecedented situation

The following graph of the yearly water level cycles in Lake Gatún demonstrates possible consequences, aggravated by the ongoing climate change. In spite of reforestation activities, from around 2015 onwards, i.e. on the right-hand side of the graph, we see elevated water level maxima during the rainy season and diminished minima during the dry season.

Historic evolution of the water level in the Gatún Lake. Red dots correspond for strong deviations from the long-term average (which is shown in grey colour in the background). Data for El Niño / La Niña phases are scraped from

The next figure shoes the water level trend at the start of this January 2024 (red) and compares it to the historic evolution of other years (blue). The current low levels (red) have not been observed at any start of the year since data are recorded. With the dry season just starting, these low water levels can be expected to become lower still over the coming weeks and months.

Historic seasonal evolution in other years of the water level in Gatún Lake (blue) compared to the evolution of the past 20 days (in red).

Mid-term scenarios portray a disconcerting picture

The next graph visualises this statement. Starting from the current water level, we use the historic trends to create projections into the future by transferring each yearly cycle so that it starts at the current level. Starting from about March 2024, an increasing number of these scenarios yield critically low water levels:

Scenarios developed with the historical development shown in the previous graph.

Notice that, unlike a swimming pool, the area of a lake decreases together with its water level. Therefore, with the same withdrawal, 200.000 tons of water per single ship operation, the water level falls even faster at lower levels. The scenarios shown above, and their statistical analysis below, are thus likely to err on the side of optimism.

Bar a rain-miracle, the only possibility we see to avoid critically low water levels for an extended period in 2024 is to reduce significantly the canal capacity, starting now.

This would stretch out, but somewhat alleviate, the consequences.

The next graph is produced by calculating for each day the ratio of scenarios with water levels below 79 feet. Such levels impact smooth canal operations: ships may be required to unload and transport on land part of their freight. Daily capacity in ship handling is also reduced. Starting from mid-March, the likelihood for such critically low water levels rises sharply and reaches more than 70% for the month of May. A delayed onset of the rainy season would further exacerbate the situation. An elevated likelihood of low water persists until the end of October – with a non-negligeable number of scenarios under which canal operations do not recover at all throughout the year 2024.

Statistical analysis of the scenarios shown in the previous graph.

What is your recommended course of action?

To our knowledge, unfortunately, the Canal Authorities do not publish daily capacity figures. Please let us know if you have a source for these data. We anticipate the Canal Authorities to forego revenue to avoid future catastrophe and reduce the canal operations to save water. We also don’t have historic data for the cost of passing the canal (which would also be easy to publish) but anticipate the resulting scarcity of slots to drive up significantly their cost.

These alarming scenarios prompt us to question how prepared companies, their supply chain organisations and the global economy are for a potential disruption of such an extent in the Panama Canal. These scenarios for 2024 imply significant challenges for the logistics industry, with far-reaching implications for international trade.